Are
You Meeting All Six Requirements for Quality Flatwork?
Requirement #1
PROPER SUBGRADE PREPARATION
• Subgrade is the existing soil after the topsoil is
removed.
• Any pockets of soft soil that cannot be uniformly compacted
must be removed and replaced with suitable material.
• Slope the subgrade away from structures enough to ensure
good drainage.
• Never place concrete on frozen or muddy subgrade.
Requirement #2
PROPER SLAB DESIGN
• Use a minimum thickness of 4 inches.
• Control joints should be 10 feet apart each way, and
should be at least a depth of one inch, made by sawing or tooling.
• Use a center line control joint when driveways are
more than 10 feet wide.
• Isolation joints are required at existing slabs, structures,
and objects. Isolation joints should run the full depth of the
slab.
Requirement #3
PROPER CONCRETE MIX DESIGN
• The mix must be a minimum 4500 psi air entrained concrete
meeting the following requirements:
• A water/cement ratio of .45.
• Air content when placed: 6 percent, plus or minus 1
percent.
• Slump: 4 inches, plus or minus 1 inch.
• Coarse and fine aggregate: shall meet Wisconsin Department
of Transportation specifications.
• Note: The air content and strength
of the mix will be affected by any re-tempering water added
at the jobsite.
Requirement #4
PROPER PLACING AND FINISHING
• Place the concrete as near to final position as possible.
• No finishing operations shall be performed when there
is excess moisture or bleed water on the surface.
• The only finishing operations required are:
screeding or strike-off; bull floating prior to the appearance
of any bleed water; a waiting period for the water sheen to
disappear; edging and jointing; and a broom texture (the safest
and most durable final finish).
• Protection of the concrete from the hot sun, high winds,
or freezing temperatures is required until the concrete has
a chance to cure properly.
• All concrete should be placed within 90 minutes from
the time the truck was loaded. Hot-weather practices call for
shorter placement time limits.
Requirement #5
PROPER CURING AND SEALING
• Curing is a process where a satisfactory moisture content
and temperature must be maintained.
• Curing greatly increases the strength and durability
of the concrete and therefore its resistance to freezing and
thawing and de-icer salts.
• Mid-April to Mid-September: Use a sprayed on curing
compound, applied according to the
manufacturer’s recommendations.
• Mid-September to Mid-April: Use waterproof covers and
maintain curing for at least 7 days at temperatures above 40
degrees Fahrenheit. Air dry for an additional 30 days and follow
with a concrete sealer to prevent intrusion of deicing salts.
Use caution and wise cold-weather practices when placing exterior
concrete during these months.
Requirement #6
PROPER AFTERCARE
• Don’t drive on new concrete for at least 7 days.
• Don’t allow drain water to undermine the slab
and cause settlement cracks.
• Don’t allow snow and ice to accumulate on the
slab during the first year.
• Don’t allow the use of de-icing chemicals for
snow and ice removal the first winter. Sand can be used for
traction.
• Never use de-icers fertilizer ingredients such as ammonium
sulfate and ammonium nitrate. They attack and destroy concrete
by chemical action.
• Promptly remove build up snow and ice in winter and
broom off areas where deicing salts drop from vehicles.
• If wear shows in high traffic areas (as sometimes happens
after five or more years), clean the surface and reseal for
further protection.